AFFECTED SYSTEMS: enterprise cornersville ingomar martintown waterford
Wednesday Jan 10 2024 // 02:47am: Upgrades Complete
Upgrades are complete.
Tuesday Jan 9 2024 // MIDNIGHT: Network Upgrades
On Tuesday Jan. 9th 2024, starting at MIDNIGHT (01-10-2024 00:00:00) NESPARC will perform upgrades to core routers in the Enterprise substation.
Susbscribers should fail over to backup circuits, but there is the possibility that short interruptions will occur in the areas serviced on these core routers (Enterprise, Martintown, Ingomar, Cornersville and Waterford) as the updates are applied and routers are restarted.
The maintenance is expected to require 1-2 hours to complete.
Last updated: April 1, 2024 at 9:49 AM CST