AFFECTED SYSTEMS: oxford
Thu May 1 2025 7:15pm : Complete
Repairs are completed and services are restored.
Thu May 1 2025 5:15pm : In Progress
Crews are continuing to splice the new cable and test. A significant number of services have been restored and we expect restoration to be completed promptly. We will update here when crews are hands-off.
Thu May 1 2025 11:15am : In Progress
NE Fiber located a cut mainline fiber near the intersection of Belk Blvd and Hwy 7 south. The fiber was damaged by installation of water mains. Crews are on-site splicing in new fiber to replace the damaged section. All subscribers south of that intersection, serviced by Oxford Substation are affected. This area extends to the 7/9 Split and includes areas of South Lamar Blvd, Pea Ridge Road, and surrounding areas. We do not have an exact ETR at this time but crews are working speedily to resolve the outage.
We appreciate your patience while we work to continually improve the resiliency of our network. Thanks for using NESPARC.
Last updated: May 2, 2025 at 8:11 AM CST